Data analysis results of DauThau.info software for project owners Urban Upgrading Project Management Unit of Ca Mau City as follows:
- Has relationships with 2 bid solicitors.
- Has relationships with 9 contractors.
- Announced 15 development investment project, of which 1 projects that have not announced the contractor selection plan.
- Announced 5 contractor selection plans with a total of 15 bidding packages, of which 0 prequalification documents have not found the investment project
- Has invited bids for 2 packages (with 2 tender notices), conducted prequalification for 0 packages.
- Published 0 quotation requests.
- Announced the results of 7 packages, and canceled bids for 0 packages (among the packages mentioned above).
- There are 6 packages with results that do not have tender notice or prequalification notice.
- There are 0 packages with results that do not have Contractor selection plan.
- There are 3 packages that have not fully posted the contractor selection results. Of these 3 bidding packages have no tender notices found.
- On average, the number of contractors participating in each package is: 0 contractors.
- Breakdown by bidding field: Goods 0%, Construction 100.00%, Consultancy 0%, Non-consultancy 0%, Mixed 0%, Other fields 0%.
- The total value according to the packages with valid contractor selection results is: 2,453,299,950 VND, of which the total winning bid value is: 2,358,271,000 VND.
- The savings rate is: 3.87%.
Data analysis results of DauThau.info software for project owners Urban Upgrading Project Management Unit of Ca Mau City as follows:
- Has relationships with 9 contractors.
- The average number of contractors participating in each bidding package is: 0 contractors.
- Proportion of bidding fields: Goods 0%, Construction 100.00%, Consulting 0%, Non-consulting 0%, Mixed 0%, Other 0%.
- The total value according to the bidding package with valid IMP is: 2,453,299,950 VND, in which the total winning value is: 2,358,271,000 VND.
- The savings rate is: 3.87%.
| Evaluation criteria | Evaluation score |
|---|---|
| Experience | ??? |
| Financial capacity | ??? |
| Transparency of the investor/bidder | ??? |
| Bidding efficiency | ??? |
The Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted the results of the bidding package Civil Works of the investor Urban Upgrading Project Management Unit of Ca Mau City.
- Winning bidder: TAN LOC PHATCO., LTD
18/07/2023 09:34
The Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted the results of the bidding package Construction supervision of the investor Urban Upgrading Project Management Unit of Ca Mau City.
- Winning bidder: Công ty Cổ Phần Tư vấn Kiến trúc - Quy hoạch - Xây dựng Cà Mau
18/07/2023 09:25
The Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted the results of the bidding package Equipment Purchasing of the investor Urban Upgrading Project Management Unit of Ca Mau City.
- Winning bidder: CÔNG TY TNHH XÂY LẮP ĐIỆN VÀ THƯƠNG MẠI TRƯƠNG MỸ KIM
18/07/2023 09:15
The Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted the request Plan for selection of contractor for Repairing of working rooms of the City Party Committee Headquarters of the investor Urban Upgrading Project Management Unit of Ca Mau City with 3 bidding package.
05/07/2023 09:06
Urban Upgrading Project Management Unit of Ca Mau City Posted Development Investment Project Repairing office blocks of the City Party Headquarters.
05/07/2023 08:08
The Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted the results of the bidding package Construction supervision of the investor Urban Upgrading Project Management Unit of Ca Mau City.
- Winning bidder: CÔNG TY TNHH TƯ VẤN VÀ ĐẦU TƯ XÂY DỰNG HOÀN MỸ
07/11/2022 10:56
The Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted the results of the bidding package Construction work and equipment installation of the investor Urban Upgrading Project Management Unit of Ca Mau City.
- Winning bidder: CÔNG TY TNHH MỘT THÀNH VIÊN THƯƠNG MẠI TOÀN GIA KHÁNH
27/10/2022 17:25
Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted Tender Notice Construction work and equipment installation of the investor Urban Upgrading Project Management Unit of Ca Mau City with the form Competitive Offer.
06/10/2022 14:56
The Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted the results of the bidding package Evaluation of bidding documents and contractor selection results of the investor Urban Upgrading Project Management Unit of Ca Mau City.
- Winning bidder: TU VAN & DICH VU CUU LONG A MEMBER COMPANY LIMITED
05/10/2022 16:57
The Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted the results of the bidding package Prepare bidding documents and evaluate bids of the investor Urban Upgrading Project Management Unit of Ca Mau City.
- Winning bidder: HOP NHAT CONSTRUCTION INVESTMENT CONSULTING COMPANY LIMITED
30/09/2022 09:31
The data sheet has been partially hidden, to see the full information please Login or Register
Urban Upgrading Project Management Unit of Ca Mau City announced the results of the bid package Civil Works .
- Winning bidder: TAN LOC PHATCO., LTD
18/07/2023 09:34
Urban Upgrading Project Management Unit of Ca Mau City announced the results of the bid package Construction supervision .
- Winning bidder: Công ty Cổ Phần Tư vấn Kiến trúc - Quy hoạch - Xây dựng Cà Mau
18/07/2023 09:25
Urban Upgrading Project Management Unit of Ca Mau City announced the results of the bid package Equipment Purchasing .
- Winning bidder: CÔNG TY TNHH XÂY LẮP ĐIỆN VÀ THƯƠNG MẠI TRƯƠNG MỸ KIM
18/07/2023 09:15
Urban Upgrading Project Management Unit of Ca Mau City publishes the plan Plan for selection of contractor for Repairing of working rooms of the City Party Committee Headquarters with 3 bidding package .
05/07/2023 09:06
Urban Upgrading Project Management Unit of Ca Mau City announced the results of the bid package Construction supervision .
- Winning bidder: CÔNG TY TNHH TƯ VẤN VÀ ĐẦU TƯ XÂY DỰNG HOÀN MỸ
07/11/2022 10:56
Urban Upgrading Project Management Unit of Ca Mau City announced the results of the bid package Evaluation of bidding documents and contractor selection results .
- Winning bidder: TU VAN & DICH VU CUU LONG A MEMBER COMPANY LIMITED
05/10/2022 16:57
Urban Upgrading Project Management Unit of Ca Mau City announced the results of the bid package Prepare bidding documents and evaluate bids .
- Winning bidder: HOP NHAT CONSTRUCTION INVESTMENT CONSULTING COMPANY LIMITED
30/09/2022 09:31
Urban Upgrading Project Management Unit of Ca Mau City publishes the plan Plan for selection of contractor for Fire protection system installation project Phan Boi Chau Secondary School, Ward 4, Ca Mau City with 4 bidding package .
29/09/2022 11:11
The data sheet has been partially hidden, to see the full information please Login or Register
The Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted the results of the bidding package Civil Works of the investor Urban Upgrading Project Management Unit of Ca Mau City.
- Winning bidder: TAN LOC PHATCO., LTD
18/07/2023 09:34
The Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted the results of the bidding package Construction supervision of the investor Urban Upgrading Project Management Unit of Ca Mau City.
- Winning bidder: Công ty Cổ Phần Tư vấn Kiến trúc - Quy hoạch - Xây dựng Cà Mau
18/07/2023 09:25
The Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted the results of the bidding package Equipment Purchasing of the investor Urban Upgrading Project Management Unit of Ca Mau City.
- Winning bidder: CÔNG TY TNHH XÂY LẮP ĐIỆN VÀ THƯƠNG MẠI TRƯƠNG MỸ KIM
18/07/2023 09:15
The Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted the request Plan for selection of contractor for Repairing of working rooms of the City Party Committee Headquarters of the investor Urban Upgrading Project Management Unit of Ca Mau City with 3 bidding package.
05/07/2023 09:06
Urban Upgrading Project Management Unit of Ca Mau City Posted Development Investment Project Repairing office blocks of the City Party Headquarters.
05/07/2023 08:08
The Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted the results of the bidding package Construction supervision of the investor Urban Upgrading Project Management Unit of Ca Mau City.
- Winning bidder: CÔNG TY TNHH TƯ VẤN VÀ ĐẦU TƯ XÂY DỰNG HOÀN MỸ
07/11/2022 10:56
The Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted the results of the bidding package Construction work and equipment installation of the investor Urban Upgrading Project Management Unit of Ca Mau City.
- Winning bidder: CÔNG TY TNHH MỘT THÀNH VIÊN THƯƠNG MẠI TOÀN GIA KHÁNH
27/10/2022 17:25
Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted Tender Notice Construction work and equipment installation of the investor Urban Upgrading Project Management Unit of Ca Mau City with the form Competitive Offer.
06/10/2022 14:56
The Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted the results of the bidding package Evaluation of bidding documents and contractor selection results of the investor Urban Upgrading Project Management Unit of Ca Mau City.
- Winning bidder: TU VAN & DICH VU CUU LONG A MEMBER COMPANY LIMITED
05/10/2022 16:57
The Bid solicitor Urban Upgrading Project Management Unit of Ca Mau City has posted the results of the bidding package Prepare bidding documents and evaluate bids of the investor Urban Upgrading Project Management Unit of Ca Mau City.
- Winning bidder: HOP NHAT CONSTRUCTION INVESTMENT CONSULTING COMPANY LIMITED
30/09/2022 09:31
The data sheet has been partially hidden, to see the full information please Login or Register
Summary: Investor Urban Upgrading Project Management Unit of Ca Mau City is the investor of 15 development investment project develop. The data sheet has been partially hidden, to see the full information please Login or Register
To receive this bid solicitor's earliest contractor selection plan by email, please create register for the VIP2 package.
Summary: Investor Urban Upgrading Project Management Unit of Ca Mau City is the owner of 5 contractor selection plan. In which, they self-invite 1 of contractor selection plan, other units invite bids of 4 of contractor selection plan.
To receive the earliest Tender Notice of this Bid solicitor via email, please register for the VIP1 package.
Summary: Investor Urban Upgrading Project Management Unit of Ca Mau City is the investor of 2 package, of which 0 package is self-invited, other units invite bid 2 package. The data sheet has been partially hidden, to see the full information please Login or Register
Summary: Investor Urban Upgrading Project Management Unit of Ca Mau City is the owner of 7 contractor selection result. The data sheet has been partially hidden, to see the full information please Login or Register
Summary: The investor Urban Upgrading Project Management Unit of Ca Mau City has a relationship with 2 procuring entities. The data sheet has been partially hidden, to see the full information please Login or Register
Summary: Investor Urban Upgrading Project Management Unit of Ca Mau City is an investor with 9 contractor. The data sheet has been partially hidden, to see the full information please Login or Register