Bidder Selection Plan

Adjusting the contractor selection plan for phase 3 - Gia Loc 220kV Transformer Station Project and connection lines

  Watching      
Find: 10:43 15/05/2024
Contractor Selection Plan ID
PL2300121812-03
Publishing time
10:42 15/05/2024
Posting Status
Published
Contractor selection plan name
Adjusting the contractor selection plan for phase 3 - Gia Loc 220kV Transformer Station Project and connection lines
Project management forms
Another form
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20210962824-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Location
Authority that issues the decision
TỔNG CÔNG TY TRUYỀN TẢI ĐIỆN QUỐC GIA
Approval date
14/05/2024
Approval ID
765/QĐ-EVNNPT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Filter name, Highest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Filter name, Investor, Bidding package number, Lowest bid price, Highest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 6
1.Tender package No 10a: Supply and transport of secondary VTTB, information VTTB
Tender/ Prequalification Notice ID
Contract execution period
6 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
May 2024
Type of contract
All in One
Prequalification
No
Location
Gia Lộc District, Hải Dương
2.Tender package No 10b: Supply of equipment and software of computer control system
Tender/ Prequalification Notice ID
Contract execution period
6 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
May 2024
Type of contract
All in One
Prequalification
No
Location
Gia Lộc District, Hải Dương
3.Package 16: Providing installation services, connecting and integrating protection control systems; Install transformers; Calibration and safety testing of equipment
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVNNPT
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January 2024
Type of contract
All in One
Prequalification
No
Location
4.Package 15: Supply and installation of fire protection system
Tender/ Prequalification Notice ID
Contract execution period
3 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
October 2024
Type of contract
All in One
Prequalification
No
Location
Gia Lộc District, Hải Dương
5.Tender package No 19: Audit of the completed project settlement report
Tender/ Prequalification Notice ID
Contract execution period
2 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
December 2024
Type of contract
All in One
Prequalification
No
Location
Gia Lộc District, Hải Dương
6.Tender package No 22: Training and coaching of cultural management staff
Tender/ Prequalification Notice ID
Contract execution period
4 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVNNPT
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Gia Lộc District, Hải Dương

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Adjusting the contractor selection plan for phase 3 - Gia Loc 220kV Transformer Station Project and connection lines". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Adjusting the contractor selection plan for phase 3 - Gia Loc 220kV Transformer Station Project and connection lines" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 14

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 8602 Projects are waiting for contractors
  • 1126 Tender notices posted in the last 24 hours
  • 1903 Contractor selection plan posted in the last 24 hours
  • 25350 Tender notices posted in the past month
  • 40449 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second