Bidder Selection Plan

Construction planning: Traffic road in Eo Ken village, Thanh Son commune (From fig tree to Po Hang area, Eo Ken village)

  Watching      
Find: 10:22 03/10/2023
Contractor Selection Plan ID
PL2300181127-00
Publishing time
09:56 03/10/2023
Posting Status
Published
Contractor selection plan name
Construction planning: Traffic road in Eo Ken village, Thanh Son commune (From fig tree to Po Hang area, Eo Ken village)
Investment objective
- Realize the commune's socio-economic development plan; - Promote the effectiveness of infrastructure investment, contributing to sustainable poverty reduction; protect the environment, build new rural areas and strengthen security and defense; - Synchronize the transportation system to meet the needs of travel and trade and ensure safety for employees.
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300048049-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Location
Thanh Hoa province
Authority that issues the decision
UỶ BAN NHÂN DÂN XÃ THÀNH SƠN
Approval date
19/09/2023
Approval ID
110/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 5
1.Bidding package No. 5: Inspection costs independent math
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Capital sources of the national target program for socio-economic development in ethnic minority and mountainous areas in the period 2021 - 2030, phase I from 2021 to 2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
2.Bidding package No. 2: Consulting supervision construction supervision
Tender/ Prequalification Notice ID
Contract execution period
6 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Capital sources of the national target program for socio-economic development in ethnic minority and mountainous areas in the period 2021 - 2030, phase I from 2021 to 2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
3.Bidding package No. 4: Consulting appraisal determination of bidding documents and appraisal KQLCNT
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Capital sources of the national target program for socio-economic development in ethnic minority and mountainous areas in the period 2021 - 2030, phase I from 2021 to 2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
4.Bidding package No. 3: Construction works (including provisions and construction insurance)
Tender/ Prequalification Notice ID
Contract execution period
6 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Capital sources of the national target program for socio-economic development in ethnic minority and mountainous areas in the period 2021 - 2030, phase I from 2021 to 2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
5.Bidding package number 1: Consulting Bidding documents, evaluation of bidding documents
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Capital sources of the national target program for socio-economic development in ethnic minority and mountainous areas in the period 2021 - 2030, phase I from 2021 to 2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Construction planning: Traffic road in Eo Ken village, Thanh Son commune (From fig tree to Po Hang area, Eo Ken village)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Construction planning: Traffic road in Eo Ken village, Thanh Son commune (From fig tree to Po Hang area, Eo Ken village)" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 3

You did not use the site, Click here to remain logged. Timeout: 60 second