Bidder Selection Plan

Contractor selection plan for phase 1 of the project: New construction of Phan Boi Chau High School for the Gifted (phase 2)

  Watching      
Find: 15:10 15/05/2024
Contractor Selection Plan ID
PL2400080295-00
Publishing time
15:10 15/05/2024
Posting Status
Published
Contractor selection plan name
Contractor selection plan for phase 1 of the project: New construction of Phan Boi Chau High School for the Gifted (phase 2)
Investment objective
Synchronize and modernize the facilities of Phan Boi Chau High School for the Gifted, thereby meeting the requirements of training talents and high-quality human resources in the period of international integration; contributing to fundamental and comprehensive innovation of education and training, meeting the requirements of industrialization and modernization in the context of a socialist-oriented market economy and international integration.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300036918-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
4 Years
Location
Authority that issues the decision
Ủy ban nhân dân tỉnh Nghệ An
Approval date
14/05/2024
Approval ID
1167/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 5
1.Tender package No 02: Consulting on geological survey, preparing construction drawing design and total estimate
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Central budget sources in the medium-term public investment plan and local budget sources
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Vinh City, Nghệ An
2.Bid package number 03: Consulting on preparing E-Bidding documents and evaluating E-Bidding documents for bidding package number 02
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Central budget sources in the medium-term public investment plan; Local budget sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
3.Bidding package No. 04: Consulting on E-HSMT appraisal and appraisal of contractor selection results for bidding package No. 02
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Central budget sources in the medium-term public investment plan and local budget sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Vinh City, Nghệ An
4.Bidding package No. 05: Consulting on equipment price appraisal
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Central budget sources in the medium-term public investment plan and local budget sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Vinh City, Nghệ An
5.Tender package No 06: Consulting on verification of construction drawing design and total cost estimate
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Central budget sources in the medium-term public investment plan and local budget sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Vinh City, Nghệ An

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan for phase 1 of the project: New construction of Phan Boi Chau High School for the Gifted (phase 2)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan for phase 1 of the project: New construction of Phan Boi Chau High School for the Gifted (phase 2)" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 9

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 8382 Projects are waiting for contractors
  • 1063 Tender notices posted in the last 24 hours
  • 1894 Contractor selection plan posted in the last 24 hours
  • 25335 Tender notices posted in the past month
  • 40501 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second