Bidder Selection Plan

Project contractor selection plan: Renovating and upgrading roads from Provincial Road 516C, Dinh Hoa Commune to Provincial Road 516D, Dinh Tien Commune, Yen Dinh District

  Watching      
Find: 10:55 12/07/2024
Contractor Selection Plan ID
PL2400074513-01
Publishing time
10:54 12/07/2024
Posting Status
Published
Contractor selection plan name
Project contractor selection plan: Renovating and upgrading roads from Provincial Road 516C, Dinh Hoa Commune to Provincial Road 516D, Dinh Tien Commune, Yen Dinh District
Investment objective
Create favorable traffic conditions for people's travel, production, socio-economic development, tourism and trade; At the same time, gradually improve the transportation network of communes and districts; enhance traffic connectivity between provincial roads, improve transport capacity; Improve the material and spiritual life of local people, contributing to the completion of the goal of building an advanced new rural area, a model for communes passing through as well as Yen Dinh district.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400021026-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
3 Years
Location
Authority that issues the decision
UBND huyện yên Định
Approval date
10/07/2024
Approval ID
2632/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Highest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 11
1.Bidding package No. 01: Consulting on survey, design of financial protection and project area
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget support is 22.4 billion VND, the remaining 9.6 billion VND is provided by the district budget.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Yên Định District, Thanh Hoá
2.Bidding package No. 02: Consulting and supervision of survey work for TKBVTC and DT steps
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget support is 22.4 billion VND, the remaining 9.6 billion VND is provided by the district budget.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Yên Định District, Thanh Hoá
3.Tender package No 03: Consultancy on verification of TKBVTC and DT
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget support is 22.4 billion VND, the remaining 9.6 billion VND is provided by the district budget.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Yên Định District, Thanh Hoá
4.Tender package No 04: Consulting Environmental Impact Assessment Report
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget support is 22.4 billion VND, the remaining 9.6 billion VND is provided by the district budget.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Yên Định District, Thanh Hoá
5.Bidding package No. 05: Consulting on preparing bidding documents, evaluating bid documents for construction packages
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget support is 22.4 billion VND, the remaining 9.6 billion VND is provided by the district budget.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Yên Định District, Thanh Hoá
6.Bidding package No. 06: Consulting on appraisal of bidding documents, results of contractor selection for construction packages
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget support is 22.4 billion VND, the remaining 9.6 billion VND is provided by the district budget.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Yên Định District, Thanh Hoá
7.Bidding package No. 07: Consulting on preparing bidding documents, evaluating bid documents, construction supervision consulting package
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget support is 22.4 billion VND, the remaining 9.6 billion VND is provided by the district budget.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Yên Định District, Thanh Hoá
8.Bidding package No. 08: Consulting on appraisal of bidding documents, contractor selection results, construction supervision consulting package
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget support is 22.4 billion VND, the remaining 9.6 billion VND is provided by the district budget.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Yên Định District, Thanh Hoá
9.Tender package No 09: Consulting on site clearance pile installation
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget support is 22.4 billion VND, the remaining 9.6 billion VND is provided by the district budget.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Yên Định District, Thanh Hoá
10.Bidding package No. 10: Construction work (Including construction insurance)
Tender/ Prequalification Notice ID
Contract execution period
540 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget support is 22.4 billion VND, the remaining 9.6 billion VND is provided by the district budget.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
According to adjusted unit price
Prequalification
No
Location
Yên Định District, Thanh Hoá
11.Tender package No 11: Construction supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
540 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget support is 22.4 billion VND, the remaining 9.6 billion VND is provided by the district budget.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Yên Định District, Thanh Hoá

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project contractor selection plan: Renovating and upgrading roads from Provincial Road 516C, Dinh Hoa Commune to Provincial Road 516D, Dinh Tien Commune, Yen Dinh District". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project contractor selection plan: Renovating and upgrading roads from Provincial Road 516C, Dinh Hoa Commune to Provincial Road 516D, Dinh Tien Commune, Yen Dinh District" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 12

You did not use the site, Click here to remain logged. Timeout: 60 second