Bidder Selection Plan

Project contractor selection plan: Road in Thuong Son village, Dien Thuong commune, Ba Thuoc district (section 1: from Mr. Van Thung's house to Ngua mountain; section 2: from spillway to Mr. Ngan Van Thuc's house).

  Watching  
Project Contractor selection plan Bid award
Find: 04:56 30/08/2023
Contractor Selection Plan ID
PL2300148238-03
Publishing time
04:55 30/08/2023
Posting Status
Published
Contractor selection plan name
Project contractor selection plan: Road in Thuong Son village, Dien Thuong commune, Ba Thuoc district (section 1: from Mr. Van Thung's house to Ngua mountain; section 2: from spillway to Mr. Ngan Van Thuc's house).
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300039467-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
12 Month
Location
Thanh Hoa province
Authority that issues the decision
UBND xã Điền Thượng
Approval date
21/08/2023
Approval ID
301/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Publication date (View changes)

- Change: Publication date (View changes)

- Change: Publication date (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 2
1.Tender package No 02: Construction work
Tender/ Prequalification Notice ID
Contract execution period
3 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Central budget source according to Resolution No. 370/NQ-HDND dated March 24, 2023 of the People's Council of Thanh Hoa province, term XVIII, 12th session.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
2.Package 01: Construction supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
3 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Central budget source according to Resolution No. 370/NQ-HDND dated March 24, 2023 of the People's Council of Thanh Hoa province, term XVIII, 12th session.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project contractor selection plan: Road in Thuong Son village, Dien Thuong commune, Ba Thuoc district (section 1: from Mr. Van Thung's house to Ngua mountain; section 2: from spillway to Mr. Ngan Van Thuc's house).". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project contractor selection plan: Road in Thuong Son village, Dien Thuong commune, Ba Thuoc district (section 1: from Mr. Van Thung's house to Ngua mountain; section 2: from spillway to Mr. Ngan Van Thuc's house)." plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 7

You did not use the site, Click here to remain logged. Timeout: 60 second