Bidder Selection Plan

Project to develop green areas in the city in 2023: Nguyen Trung Truc Street (National Highway 1 - CMT8), Tra Quy Binh Street (Chau Van Giac - Vo Van Tan), Le Cao Dong Street (Truong Dinh - Truong Van Bang), Bui Chi Nhuan Street (Truong Dinh - Chau Van Giac), Bach Dang Street (Nguyen Trung Truc - Nguyen Hue), Chau Van Giac Street (Tra Quy Binh - Hung Vuong), Nguyen Huynh Duc Street (Lang Gate 1- Mausoleum Gate 2), Tran Trung Tam Street (Nguyen Dinh Chieu - Chau Thi Kim)

  Watching      
Find: 16:54 08/11/2023
Contractor Selection Plan ID
PL2300215287-00
Publishing time
16:36 08/11/2023
Posting Status
Published
Contractor selection plan name
Project to develop green areas in the city in 2023: Nguyen Trung Truc Street (National Highway 1 - CMT8), Tra Quy Binh Street (Chau Van Giac - Vo Van Tan), Le Cao Dong Street (Truong Dinh - Truong Van Bang), Bui Chi Nhuan Street (Truong Dinh - Chau Van Giac), Bach Dang Street (Nguyen Trung Truc - Nguyen Hue), Chau Van Giac Street (Tra Quy Binh - Hung Vuong), Nguyen Huynh Duc Street (Lang Gate 1- Mausoleum Gate 2), Tran Trung Tam Street (Nguyen Dinh Chieu - Chau Thi Kim)
Investment objective
To beautify the city, combat climate change, protect the environment, increase green areas, and improve air quality for the city towards a civilized, green - clean - beautiful urban area. Improve the criteria and quality of class II urban areas, strive to build Tan An city to soon complete the criteria for class I urban areas according to the Resolution of the Executive Committee of the Party Committee of Tan An city for the term 2020 - 2025
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300055866-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Location
Long An province
Authority that issues the decision
UBND thành phố Tân An
Approval date
07/11/2023
Approval ID
3326/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 4
1.Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government Budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
2.Construction supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government Budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
3.Consultancy on making request dossiers, evaluating proposals
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government Budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
4.Construction
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government Budget
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project to develop green areas in the city in 2023: Nguyen Trung Truc Street (National Highway 1 - CMT8), Tra Quy Binh Street (Chau Van Giac - Vo Van Tan), Le Cao Dong Street (Truong Dinh - Truong Van Bang), Bui Chi Nhuan Street (Truong Dinh - Chau Van Giac), Bach Dang Street (Nguyen Trung Truc - Nguyen Hue), Chau Van Giac Street (Tra Quy Binh - Hung Vuong), Nguyen Huynh Duc Street (Lang Gate 1- Mausoleum Gate 2), Tran Trung Tam Street (Nguyen Dinh Chieu - Chau Thi Kim)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project to develop green areas in the city in 2023: Nguyen Trung Truc Street (National Highway 1 - CMT8), Tra Quy Binh Street (Chau Van Giac - Vo Van Tan), Le Cao Dong Street (Truong Dinh - Truong Van Bang), Bui Chi Nhuan Street (Truong Dinh - Chau Van Giac), Bach Dang Street (Nguyen Trung Truc - Nguyen Hue), Chau Van Giac Street (Tra Quy Binh - Hung Vuong), Nguyen Huynh Duc Street (Lang Gate 1- Mausoleum Gate 2), Tran Trung Tam Street (Nguyen Dinh Chieu - Chau Thi Kim)" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 3

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 8219 Projects are waiting for contractors
  • 1057 Tender notices posted in the last 24 hours
  • 1702 Contractor selection plan posted in the last 24 hours
  • 24282 Tender notices posted in the past month
  • 38463 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second