Bidder Selection Plan

Technical infrastructure of resettlement and new residential areas - Phase 1, Tan Ngoc village, Truong Giang commune, Nong Cong district

  Watching      
Find: 17:42 19/05/2024
Contractor Selection Plan ID
PL2400083740-00
Publishing time
17:41 19/05/2024
Posting Status
Published
Contractor selection plan name
Technical infrastructure of resettlement and new residential areas - Phase 1, Tan Ngoc village, Truong Giang commune, Nong Cong district
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400023354-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
12 Month
Authority that issues the decision
UBND huyện Nông Cống
Approval date
15/05/2024
Approval ID
2452/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 3
1.Tender package No 01: Consultancy on preparation of Bid Documents and Bid Evaluation
Tender/ Prequalification Notice ID
Contract execution period
1 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bidding documents and evaluate bids
Capital source details
From the source of payment for resettlement land use fees and the source of auctions to grant land use rights at the planning site of the resettlement and new residential area in Truong Giang commune.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Nông Cống District, Thanh Hoá
Implementation location (Before merge)
Thanh Hoa province
2.Package 02: Construction and installation of construction equipment
Tender/ Prequalification Notice ID
Contract execution period
6 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out construction and installation of construction equipment
Capital source details
From the source of payment for resettlement land use fees and the source of auctions to grant land use rights at the planning site of the resettlement and new residential area in Truong Giang commune.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Nông Cống District, Thanh Hoá
Implementation location (Before merge)
Thanh Hoa province
3.Package 03: Supervision of construction and installation of construction equipment
Tender/ Prequalification Notice ID
Contract execution period
6 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out construction supervision and installation of construction equipment
Capital source details
From the source of payment for resettlement land use fees and the source of auctions to grant land use rights at the planning site of the resettlement and new residential area in Truong Giang commune.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Nông Cống District, Thanh Hoá
Implementation location (Before merge)
Thanh Hoa province

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Technical infrastructure of resettlement and new residential areas - Phase 1, Tan Ngoc village, Truong Giang commune, Nong Cong district". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Technical infrastructure of resettlement and new residential areas - Phase 1, Tan Ngoc village, Truong Giang commune, Nong Cong district" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 40

You did not use the site, Click here to remain logged. Timeout: 60 second