Bidder Selection Plan

The decision on approving the plan to select a contractor to perform the bidding packages under the economic - technical report on construction investment: Renovating and upgrading An Phu pumping station under the Plan for major repair of finished assets. irrigation infrastructure in 2022

  Watching      
Find: 09:36 15/06/2023
Contractor Selection Plan ID
PL2200001410-02
Publishing time
09:28 15/06/2023
Posting Status
Published
Contractor selection plan name
The decision on approving the plan to select a contractor to perform the bidding packages under the economic - technical report on construction investment: Renovating and upgrading An Phu pumping station under the Plan for major repair of finished assets. irrigation infrastructure in 2022
Investment objective
Building An Phu pumping station with the scale of 02 horizontal pump groups responsible for irrigating 105ha and draining 145ha of land in An Phu and Gioi Te villages, Phu Lam commune, Tien Du district. Including the following main items: Factory, suction tank, discharge tank, irrigation channel, drain to the suction tank, branch drainage channel, road to the factory and protective fence. Installing 02 pumps including: 01 machine with flow Q=2,800m3/h and 01 pump with flow 1200m3/h and accompanying mechanical and electrical equipment for operation management.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2200000079-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
85 Date
Location
Authority that issues the decision
Sở Kế hoạch và Đầu tư tỉnh Bắc Ninh
Approval date
07/09/2022
Approval ID
185/QĐ-KHĐT.ĐTG
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Lowest bid price, Publication date, Bidding package information (View changes)

- Change: Publication date (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 3
1.Bidding package 2: consulting on making bidding documents, evaluating bids for package No. 1
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Capital source for major repair of irrigation infrastructure assets 2022 according to Decision No. 649/QD-UBND dated June 7, 2021 of the Chairman Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
September 2022
Type of contract
All in One
Prequalification
No
Location
2.Package 3: Construction supervision consultancy and equipment installation
Tender/ Prequalification Notice ID
Contract execution period
85 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Capital for major repair of irrigation infrastructure assets in 2022 according to Decision No. 649/QD-UBND dated June 7, 2021 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
September 2022
Type of contract
All in One
Prequalification
No
Location
3.Package 1: The entire construction and equipment (100% new), the renovation and upgrading of An Phu pumping station under the plan of major repair of irrigation infrastructure assets in 2022
Tender/ Prequalification Notice ID
Contract execution period
85 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Capital for major repair of irrigation infrastructure assets in 2022 according to Decision No. 649/QD-UBND dated June 7, 2021 of the Chairman of Bac Ninh Provincial People's Committee.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
September 2022
Type of contract
All in One
Prequalification
No
Location
Tiên Du District, Bắc Ninh

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "The decision on approving the plan to select a contractor to perform the bidding packages under the economic - technical report on construction investment: Renovating and upgrading An Phu pumping station under the Plan for major repair of finished assets. irrigation infrastructure in 2022". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "The decision on approving the plan to select a contractor to perform the bidding packages under the economic - technical report on construction investment: Renovating and upgrading An Phu pumping station under the Plan for major repair of finished assets. irrigation infrastructure in 2022" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 13

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 8535 Projects are waiting for contractors
  • 142 Tender notices posted in the last 24 hours
  • 161 Contractor selection plan posted in the last 24 hours
  • 23692 Tender notices posted in the past month
  • 37142 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second