Data analysis results of DauThau.info software for bid solicitors HYDROPOWER PROJECT MANAGEMENT BOARD No 6 as follows:
- Has relationships with 17 contractor.
- Announced 0 investment development project, of which 0 projects have not yet announced the prequalification documents.
- Announced 16 contractor selection plans with a total of 16 bidding packages, of which 14 prequalification documents have not found the investment project.
- Has invited bids for 33 packages (with 33 tender notices), and conducted prequalification for 0 packages.
- Announced the results of 22 package, and canceled bids for 0 packages (among the packages mentioned above).
- There are 6 packages with results that do not have tender notice or prequalification notice.
- There are 11 packages that have not fully posted the contractor selection results. Of these 11 bidding packages have no tender notices found.
- On average, the number of contractors participating in each package is: 1.29 contractors.
- Breakdown by bidding field: Goods 57.58%, Construction 21.21%, Consultancy 21.21%, Non-consultancy 0%, Mixed 0%, Other fields 0%.
- The total value according to the packages with valid contractor selection results is: 105,810,055,511 VND, of which the total winning bid value is: 78,057,652,232 VND.
- The savings rate is: 26.23%.
Data analysis results of DauThau.info software for bid solicitors HYDROPOWER PROJECT MANAGEMENT BOARD No 6 as follows:
- Has relationships with 17 contractor.
- The average number of contractors participating in each bidding package is: 1.29 contractors.
- Proportion of bidding fields: Goods 57.58%, Construction 21.21%, Consulting 21.21%, Non-consulting 0%, Mixed 0%, Other 0%.
- The total value according to the bidding package with valid IMP is: 105,810,055,511 VND, in which the total winning value is: 78,057,652,232 VND.
- The savings rate is: 26.23%.
This Bid solicitor is also the investor, the analysis information is as follows:
- Is the investor of 0 investment and development projects.
- As the owner of 3 Contractor selection plan in which 3 Contractor selection plan is self-published, and 0 Contractor selection plan is posted by other units.
- Being the investor of 3 bidding packages in which 3 packages are self-invited, and 0 packages are invited by other units.
Evaluation criteria | Evaluation score |
---|---|
Experience | ??? |
Financial capacity | ??? |
Transparency of the investor/bidder | ??? |
Bidding efficiency | ??? |
The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted the results of the bidding package Shopping for Land Cruiser car tires of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6.
06/11/2018 10:33
The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted the results of the bidding package Consultancy on preparation of feasibility study report for investment project to upgrade the system of opening and closing valve for the spillway of Tri An hydropower plant of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6.
30/10/2018 11:12
Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted Tender Notice Shopping for Land Cruiser car tires of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 with the form National Competitive Bidding.
26/10/2018 16:00
The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted the results of the bidding package Consulting on surveys to serve the preparation of Feasibility Report and preparation of Feasibility Report for the project of increasing the capacity of 220/110kV MBA at Tri An Hydropower Plant of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6.
- Winning bidder: Công ty Cổ phần Tư vấn Xây dựng Điện 2
25/10/2018 14:01
Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted Tender Notice Shopping for Land Cruiser car tires of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 with the form National Competitive Bidding.
18/10/2018 15:24
The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted the request KHLCNT Procurement of tires for Land Cruiser cars of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 with 1 bidding package.
17/10/2018 10:47
The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted the results of the bidding package Consulting on quality inspection of Thac Mo Extension Power Plant of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6.
04/10/2018 16:08
The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted the request Consulting on quality inspection of Thac Mo Extension Power Plant of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 with 1 bidding package.
24/09/2018 15:43
The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted the request Consultancy on preparation of feasibility study report for investment project to upgrade the system of opening and closing valve for the spillway of Tri An hydropower plant of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 with 1 bidding package.
21/09/2018 13:22
Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted Tender Notice Surveying consultancy for the preparation of technical reports and technical reports for the project to increase the capacity of transformer 220/110kV of Tri An Hydropower Plant of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 with the form National competitive bidding.
28/08/2018 09:22
The data sheet has been partially hidden, to see the full information please Login or Register
HYDROPOWER PROJECT MANAGEMENT BOARD No 6 announced the results of the bid package Shopping for Land Cruiser car tires .
- Winning bidder: CÔNG TY TNHH THƯƠNG MẠI DỊCH VỤ XUẤT NHẬP KHẨU Ô TÔ GIA PHÁT
06/11/2018 10:33
HYDROPOWER PROJECT MANAGEMENT BOARD No 6 announced the results of the bidding package Shopping for Land Cruiser car tires with 1 participating contractors .
05/11/2018 07:48
HYDROPOWER PROJECT MANAGEMENT BOARD No 6 announced the results of the bid package Consultancy on preparation of feasibility study report for investment project to upgrade the system of opening and closing valve for the spillway of Tri An hydropower plant .
- Winning bidder: Công ty Cổ phần Tư vấn Xây dựng Điện 2
30/10/2018 11:12
HYDROPOWER PROJECT MANAGEMENT BOARD No 6 publishes Tender Notice Shopping for Land Cruiser car tires in the form National Competitive Bidding .
26/10/2018 16:00
HYDROPOWER PROJECT MANAGEMENT BOARD No 6 announced the results of the bid package Consulting on surveys to serve the preparation of Feasibility Report and preparation of Feasibility Report for the project of increasing the capacity of 220/110kV MBA at Tri An Hydropower Plant .
- Winning bidder: Công ty Cổ phần Tư vấn Xây dựng Điện 2
25/10/2018 14:01
HYDROPOWER PROJECT MANAGEMENT BOARD No 6 publishes Tender Notice Shopping for Land Cruiser car tires in the form National Competitive Bidding .
18/10/2018 15:24
HYDROPOWER PROJECT MANAGEMENT BOARD No 6 publishes the plan KHLCNT Procurement of tires for Land Cruiser cars with 1 bidding package .
17/10/2018 10:47
HYDROPOWER PROJECT MANAGEMENT BOARD No 6 announced the results of the bid package Consulting on quality inspection of Thac Mo Extension Power Plant .
- Winning bidder: Công ty Cổ phần Tư vấn Công nghệ, Thiết bị và Kiểm định Xây dựng CONINCO
04/10/2018 16:08
HYDROPOWER PROJECT MANAGEMENT BOARD No 6 publishes the plan Consulting on quality inspection of Thac Mo Extension Power Plant with 1 bidding package .
24/09/2018 15:43
HYDROPOWER PROJECT MANAGEMENT BOARD No 6 publishes the plan Consultancy on preparation of feasibility study report for investment project to upgrade the system of opening and closing valve for the spillway of Tri An hydropower plant with 1 bidding package .
21/09/2018 13:22
The data sheet has been partially hidden, to see the full information please Login or Register
The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted the results of the bidding package Shopping for Land Cruiser car tires of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6.
06/11/2018 10:33
The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted the results of the bidding package Consultancy on preparation of feasibility study report for investment project to upgrade the system of opening and closing valve for the spillway of Tri An hydropower plant of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6.
30/10/2018 11:12
Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted Tender Notice Shopping for Land Cruiser car tires of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 with the form National Competitive Bidding.
26/10/2018 16:00
The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted the results of the bidding package Consulting on surveys to serve the preparation of Feasibility Report and preparation of Feasibility Report for the project of increasing the capacity of 220/110kV MBA at Tri An Hydropower Plant of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6.
- Winning bidder: Công ty Cổ phần Tư vấn Xây dựng Điện 2
25/10/2018 14:01
Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted Tender Notice Shopping for Land Cruiser car tires of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 with the form National Competitive Bidding.
18/10/2018 15:24
The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted the request KHLCNT Procurement of tires for Land Cruiser cars of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 with 1 bidding package.
17/10/2018 10:47
The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted the results of the bidding package Consulting on quality inspection of Thac Mo Extension Power Plant of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6.
04/10/2018 16:08
The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted the request Consulting on quality inspection of Thac Mo Extension Power Plant of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 with 1 bidding package.
24/09/2018 15:43
The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted the request Consultancy on preparation of feasibility study report for investment project to upgrade the system of opening and closing valve for the spillway of Tri An hydropower plant of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 with 1 bidding package.
21/09/2018 13:22
Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted Tender Notice Surveying consultancy for the preparation of technical reports and technical reports for the project to increase the capacity of transformer 220/110kV of Tri An Hydropower Plant of the investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 with the form National competitive bidding.
28/08/2018 09:22
The data sheet has been partially hidden, to see the full information please Login or Register
To receive this bid solicitor's earliest contractor selection plan by email, please create register for the VIP2 package.
Summary: The bid solicitor’s HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted 16 of the contractor selection plan, which contains 16 of the bidding package. The data sheet has been partially hidden, to see the full information please Login or Register
To receive the earliest Tender Notice of this Bid solicitor via email, please register for the VIP1 package.
Summary: The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted 33 Tender Notice in the 33 bidding package. The data sheet has been partially hidden, to see the full information please Login or Register
Summary: The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has posted 22 contractor selection result in which:The data sheet has been partially hidden, to see the full information please Login or Register
- Published the results of the 22 package, canceled the bid 0 package (among the bidding packages above).
- There are 6 packages with no results found tender notice, Prequalifying Invitation Notice.
Summary: The Bid solicitor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has a relationship with 17 contractors. The data sheet has been partially hidden, to see the full information please Login or Register
Summary: Investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 has a relationship with 1 soliciting party. The data sheet has been partially hidden, to see the full information please Login or Register
Summary: Investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 is the investor of 3 package, of which 3 package is self-invited, other units invite bid 0 package. The data sheet has been partially hidden, to see the full information please Login or Register
Summary: Investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 is the owner of 3 contractor selection plan. In which, they self-invite 3 of contractor selection plan, other units invite bids of 0 of contractor selection plan.
Summary: Investor HYDROPOWER PROJECT MANAGEMENT BOARD No 6 is an investor with 13 contractor. The data sheet has been partially hidden, to see the full information please Login or Register
If you are still not our member, please sign up.You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!
Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.
Security Code