220 kV transmission line Huoi Quang - Nghia Lo

Watching          
DauThau.info discovered that this project's data collected from the new National Bidding Network System has differences in the investor compared to the data on the old system as follows:
 ⚬ New system: Ban quản lý dự án các công trình điện miền Trung
 ⚬ Old system: National Power Transmission Corporation
In addition, the bidding information related to this project also has discrepancies regarding the investor, specifically:
- The following contractor selection plans have the investor National Power Transmission Corporation:
 ⚬ LCNT Phase 3 - 220kV Huoi Quang - Nghia Lo transmission line project

 ⚬ The plan to select the contractor for the first phase of the 220kV Huoi Quang - Nghia Lo transmission line

- The following bidding packages have the investor Central Vietnam Power Projects Management Board:
 ⚬ Package No. 1: Consulting and surveying to serve the preparation of the economic and financial accounts, the preparation of the technical and financial accounts, the technical report, the bidding documents. Environmental monitoring during construction. Measure and prepare settlement documents for site clearance compensation. Investigate the current status and reserves of forests, complete the application for the policy of changing the forest use purpose

 ⚬ Package No. 2: Consulting, supervising, surveying the period of ECO-TDT and the verification of ECO-TDT

 ⚬ Package 15: Construction insurance

 ⚬ Package 14: Construction supervision consultancy

 ⚬ Package 12: Supply and delivery of lightning arresters, insulators, optical cables and accessories
Click để xem đầy đủClick để thu gọn
Found: 22:57 19/01/2021
Project number
20201041174-00
Notice type
Real announcement
Project name
220 kV transmission line Huoi Quang - Nghia Lo
Investor ID
vnz000013163
Project Category
Group B
Project management Type
Another form
Use of ODA funds
No
Investment Total Value
To view full information please Login or Register
Project approval ID
158/QĐ-HĐTV
Project approval date
18/09/2020
Approval documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611

Contractor selection plans for this project

NO Contractor selection plan ID Contractor selection plan name Total investment
1
750.464.000.000 VND
2
750.464.000.000 VND
Total amount
1.500.928.000.000 VND

Statistical table of bidding packages under the project

Statistics by type of bidding package Statistics by form Online bidding value (billion VND) Number of bidding packages whose results have been posted
Goods Civil Works Consulting Other categories Non-Consulting Online Offline
0 0 0 0 0 0 19 0.00 5
You did not use the site, Click here to remain logged. Timeout: 60 second