DauThau.info discovered that this project's data collected from the new National Bidding Network System has differences in the investor compared to the data on the old system as follows:
⚬ New system: Công ty Điện lực Thanh Oai
⚬ Old system: Công ty Điện lực Thanh Oai
In addition, the bidding information related to this project also has discrepancies regarding the investor, specifically:
- The following contractor selection plans have the investor Công ty Điện lực Thanh Oai:
⚬ Building a 35kV line to create a loop circuit on Hong Duong branch, Highway 377E10.2- Lien Chau branch, Highway 375 E10.4
- The following bidding packages have the investor Công ty Điện lực Thanh Oai:
⚬ 04XL.XDCB-2018: Construction and installation
⚬ 04TVGS-XDCB-2018: Construction supervision and equipment installation.
Contractor selection plans for this project
NO | Contractor selection plan ID | Contractor selection plan name | Total investment |
---|---|---|---|
1
|
5.068.726.845 VND |
||
Total amount |
5.068.726.845 VND |
Statistical table of bidding packages under the project
Statistics by type of bidding package | Statistics by form | Online bidding value (billion VND) | Number of bidding packages whose results have been posted | |||||
---|---|---|---|---|---|---|---|---|
Goods | Civil Works | Consulting | Other categories | Non-Consulting | Online | Offline | ||
0 | 0 | 0 | 0 | 0 | 0 | 4 | 0.00 | 2 |