Renovating AC/DC system of 110kV substations in Tien Giang province, Installing 87B busbar differential relays, 110kV substations in Tien Giang province, Installing automatic voltage regulation relays F90 of 110kV substations in the area Tien Giang province.

Watching          
Found: 15:54 27/02/2023
Project number
PR2300007474-00
Notice type
Real announcement
Project name
Renovating AC/DC system of 110kV substations in Tien Giang province, Installing 87B busbar differential relays, 110kV substations in Tien Giang province, Installing automatic voltage regulation relays F90 of 110kV substations in the area Tien Giang province.
Project objective
In order to perfect and improve the automation level in the substation, gradually convert the remote control substation to operate the KNT substation; improve labor productivity; meet the increasing demand for power quality. At the same time, to meet the electricity grid completion project for the period 2021-2025 of the Southern Power Corporation.
Investor ID
vnz000012993
Authority
Director - Tien Giang Power Company
Project duration
3 Year
Project Category
Group C
Project management Type
The investor directly manages the project
Use of ODA funds
No
Implementation location
Tien Giang province
Investment Total Value
To view full information please Login or Register VNĐ
Amount in text format
Project approval ID
2445/QĐ-PCTG
Project approval date
14/10/2021
Approval authority
Công ty Điện lực Tiền Giang
Approval documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.To download, please Login or Register

16_2445-QD-PCTG_PADT_Lap dat Ro le_LAI_Ngay 14.10.2021.pdf
File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611

Contractor selection plans for this project

NO Contractor selection plan ID Contractor selection plan name Total investment
1
11.356.545.646 VND
Total amount
11.356.545.646 VND

Statistical table of bidding packages under the project

Statistics by type of bidding package Statistics by form Online bidding value (billion VND) Number of bidding packages whose results have been posted
Goods Civil Works Consulting Other categories Non-Consulting Online Offline
0 0 1 0 0 1 0 0.12 1
You did not use the site, Click here to remain logged. Timeout: 60 second