Construction of anti-flooding ditch system in Ma Rin 2 village (Section of Sao Mai Kindergarten to Song Ba), Ia Pa commune

Watching      
Project Overall procurement plan Contractor selection plan Contractor selection result
Found: 14:33 26/08/2026
Project number
PR2600036867-01
Notice type
Real announcement
Project name
Construction of anti-flooding ditch system in Ma Rin 2 village (Section of Sao Mai Kindergarten to Song Ba), Ia Pa commune
Project objective
Solve drainage problems during rainy and flood seasons, create convenient travel conditions, develop household economies in the area, and stabilize people's lives. Resolve environmental pollution and improve the lives of local ethnic minorities. Contribute to building new rural infrastructure and improving environmental landscape, preventing soil erosion, creating conditions for growing trees and other environmental benefits.
Investor ID
vnz000043663
Authority
Ia Pa Commune People's Committee
Project duration
2026 Year
Project Category
Group C
Project management Type
The investor directly manages the project
Use of ODA funds
No
Implementation location
Xã Ia Pa, ProvinceGia Lai
Investment Total Value
To view full information please Login or Register
Project approval ID
1421/QĐ-UBND
Project approval date
22/08/2026
Approval authority
UBND xã Ia Pa
Approval documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Project versions

Contractor selection plans for this project

NO Contractor selection plan ID Contractor selection plan name Total investment
1
97.885.000 VND
Total amount
97.885.000 VND

Statistical table of bidding packages under the project

Statistics by type of bidding package Statistics by form Online bidding value (billion VND) Number of bidding packages whose results have been posted
Goods Civil Works Consulting Other categories Non-Consulting Online Offline
0 0 2 0 0 0 2 0.00 2
You did not use the site, Click here to remain logged. Timeout: 60 second