Minh Hoa 110kV substation and connection

Watching    
Project Overall procurement plan Contractor selection plan
Found: 08:04 27/07/2026
Project number
PR2600049816-00
Notice type
Real announcement
Project name
Minh Hoa 110kV substation and connection
Project objective
- Meet the demand for load growth, ensure electricity supply for socio-economic development and in accordance with local planning; - Coordinate, support and reserve capacity back and forth with Tuyen Hoa 110kV transformer station. Increasing regional power capacity, contributing to improving the reliability and safety of electricity supply, reducing power loss to the grid and improving regional electricity quality; - Gradually complete the 110kV power grid structure according to the approved Planning, ensuring technical standards and operational safety.
Investor ID
vn0400101394
Authority
Ngo Tan Cu
Project duration
4 Year
Project Category
Group C
Project management Type
Specialized Management Board - Region
Use of ODA funds
No
Implementation location
Xã Minh Hóa, ProvinceQuảng Trị
Investment Total Value
To view full information please Login or Register
Project approval ID
3173/QĐ-EVNCPC
Project approval date
25/07/2026
Approval authority
TỔNG CÔNG TY ĐIỆN LỰC MIỀN TRUNG
Approval documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Contractor selection plans Link
The project does not have any NTFP yet
You did not use the site, Click here to remain logged. Timeout: 60 second