Prevent overload, improve the grid, reduce power loss, medium and low voltage power grid and substation in Phu Ninh area, DL Tien Phuoc in 2024

Watching        
Project Overall procurement plan Contractor selection plan Tender Notice Contractor selection result
Found: 17:43 18/10/2023
Project number
PR2300051309-00
Notice type
Real announcement
Project name
Prevent overload, improve the grid, reduce power loss, medium and low voltage power grid and substation in Phu Ninh area, DL Tien Phuoc in 2024
Project objective
- To improve electricity quality, ensure stable and safe electricity supply to serve local socio-economic development, businesses and people. - Gradually improve and complete the regional power grid: ensure reliability according to the roadmap; Complete the current power grid; Reduce power supply radius, power concave area, rear wire length Households pull meters to use, resolving urgent recommendations of voters, people and local authorities.
Investor ID
vnz000022501
Authority
Director of Quang Nam Power Company
Project duration
180 Day
Project Category
Group C
Project management Type
The investor directly manages the project
Use of ODA funds
No
Implementation location
Huyện Phú Ninh, Quang Nam province
Investment Total Value
To view full information please Login or Register VNĐ
Amount in text format
Project approval ID
4812/QĐ-QNaPC
Project approval date
10/09/2023
Approval authority
Công ty Điện lực Quảng Nam
Approval documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.To download, please Login or Register

4812. QDPD BCKTKT Phu Ninh 24.pdf
File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611

Contractor selection plans for this project

NO Contractor selection plan ID Contractor selection plan name Total investment
1
8.516.647.374 VND
Total amount
8.516.647.374 VND

Statistical table of bidding packages under the project

Statistics by type of bidding package Statistics by form Online bidding value (billion VND) Number of bidding packages whose results have been posted
Goods Civil Works Consulting Other categories Non-Consulting Online Offline
0 0 2 0 0 0 2 0.00 2
You did not use the site, Click here to remain logged. Timeout: 60 second