Status
Complete opening of technical documents
Bidding package name
Bidding package 1: Survey consulting, feasibility study report preparation, implementation design after basic design, preparation of bidding documents.
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
New construction of 110kV Son Tay 3 transformer station (Son Tay 2) and branch
Contract execution period
335 day
Contractor selection methods
Competitive Bidding
Contract Type
Package and fixed unit price
Award date
10:00 20/12/2025
Bid opening completion time
10:14 20/12/2025
Tender value
Complete opening of technical documents without bidding package price
Total Number of Bidders
2
Technical Evaluation
Number Right Scoring (NR)
Estimated price
4.421.685.438 VND