Status
Tender opening completed
Bidding package name
Civil Works
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Selecting a contractor to upgrade Thay Bua dam
Contract execution period
90 day
Contractor selection methods
Competitive Offer
Award date
09:00 24/04/2024
Bid opening completion time
09:03 24/04/2024
Total Number of Bidders
4
Technical Evaluation
Number Right Scoring (NR)