Status
Tender opening completed
Bidding package name
Construction
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Reinforcing, overcoming landslides, embankment on the left bank of betel canal (from Chanh My Primary School to Bien Quan Tay Ho), Chanh My Ward
Contract execution period
90 day
Contractor selection methods
Competitive Bidding
Award date
08:00 06/06/2025
Bid opening completion time
09:55 06/06/2025
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)