Status
Tender opening completed
Bidding package name
Construction and equipment installation
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Work items: Renovating and supplementing the fire protection system - MDF1 . line
Contract execution period
120 day
Contractor selection methods
Competitive Bidding
Award date
09:00 19/06/2023
Bid opening completion time
09:21 19/06/2023
Total Number of Bidders
2
Technical Evaluation
Number Right Scoring (NR)