Construction and installation of construction equipment Solving overload of power grid in My Tho Power area
Investor
Công ty Điện lực Tiền Giang
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
The plan to select the contractor for the project Solve the overload of the grid in My Tho Power area
Contract execution period
150 day
Contractor selection methods
Competitive Bidding
Award date
15:00 08/08/2023
Bid opening completion time
15:04 08/08/2023
Total Number of Bidders
3
Technical Evaluation
Number Right Scoring (NR)
Price Tender value
5.961.066.000 VND