Status
Complete opening of financial documents
Bidding package name
Construction supervision and equipment installation
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Project contractor selection plan: Installing 02 110kV Co Chien substations
Contract execution period
160 day
Contractor selection methods
Competitive Bidding
Award date
09:00 31/05/2023
Bid opening completion time
09:26 31/05/2023
Total Number of Bidders
2
Technical Evaluation
Number Right Scoring (NR)
Estimated price
430.511.669 VND