Status
Complete opening of financial documents
Bidding package name
Construction survey and construction drawing design, making estimates
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Project planning: irrigating the western area of Vam Co Dong River phase 2 (solidifying the main canal, channel level 1, 2, 3 and channel pepper)
Contract execution period
45 day
Contractor selection methods
Competitive Bidding
Contract Type
Package and Fixed price
Award date
09:00 15/04/2024
Bid opening completion time
09:07 15/04/2024
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)
Estimated price
10.419.564.000 VND