Status
Tender opening completed
Bidding package name
Construction + Taxes, natural resources fees and mineral exploitation rights fees
Investor
Ban Quan ly du an cac cong trinh xay dung Khanh Son
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
LCNT plan for the construction phase of the project: Anti-erosion embankment of To Hap river bank section through Son Hiep and Son Binh communes
Contract execution period
300 day
Contractor selection methods
Competitive Bidding
Award date
09:00 24/09/2024
Bid opening completion time
09:12 24/09/2024
Total Number of Bidders
3
Technical Evaluation
Number Right Scoring (NR)