Status
Complete opening of financial documents
Bidding package name
Consulting survey, making feasibility study report
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
The contractor selection plan for the project preparation phase (surveying, preparing a feasibility study report), the project of drainage water system to downstream
Contract execution period
120 day
Contractor selection methods
Competitive Bidding
Award date
09:00 05/07/2025
Bid opening completion time
09:03 05/07/2025
Total Number of Bidders
4
Technical Evaluation
Number Right Scoring (NR)
Estimated price
5.075.294.170 VND
View by batch