Status
Tender opening completed
Bidding package name
Package 01: Construction work
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Project contractor selection plan: Bridge across stream from Sop Cop - Muong Lan road to Hoc Mot village (formerly Na Mot village), Muong Va commune, Sop Cop district
Contract execution period
360 day
Contractor selection methods
Competitive Bidding
Contract Type
According to fixed unit price
Award date
08:00 07/03/2024
Bid opening completion time
08:09 07/03/2024
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)
Estimated price
2.690.555.291 VND
View by batch
View by contractor