Status
Tender opening completed
Bidding package name
Package 02: Construction + equipment
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Newly opened, concrete road construction from Ta Lung Village to Kho Tau Village
Contract execution period
240 day
Contractor selection methods
Competitive Bidding
Award date
09:00 28/08/2026
Bid opening completion time
09:03 28/08/2026
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)