Status
Tender opening completed
Bidding package name
Package 03: Construction and installation
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Ayun Ha canal system repair and upgrade project
Contract execution period
150 day
Contractor selection methods
Competitive Offer
Contract Type
According to fixed unit price
Award date
09:00 14/07/2026
Bid opening completion time
10:21 14/07/2026
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)