Status
Tender opening completed
Bidding package name
Package 04: Construction and equipment procurement and installation
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Plan for selecting contractors for the project implementation phase: New construction of the headquarters of the Military Command of Dai Dong commune
Contract execution period
300 day
Contractor selection methods
Competitive Bidding
Award date
10:00 30/09/2024
Bid opening completion time
10:15 30/09/2024
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)