Status
Tender opening completed
Bidding package name
Package 05: Construction and installation
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Project contractor selection plan: Investment in building roads to Vong La Secondary School
Contract execution period
400 day
Contractor selection methods
Competitive Bidding
Contract Type
According to the adjusted unit price
Award date
15:00 21/06/2025
Bid opening completion time
15:16 21/06/2025
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)