Status
Tender opening completed
Bidding package name
Package 06: Construction cost
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Maintenance and repair of facilities serving Hue Stadium competitions
Contract execution period
10 day
Contractor selection methods
Competitive Offer
Award date
09:00 31/08/2024
Bid opening completion time
09:52 31/08/2024
Total Number of Bidders
2
Technical Evaluation
Number Right Scoring (NR)