Status
Complete opening of financial documents
Bidding package name
Package 06: Construction supervision consultancy
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Install T3, T4 110kV Tay Ho Tay substation
Contract execution period
240 day
Contractor selection methods
Competitive Bidding
Award date
14:00 12/12/2025
Bid opening completion time
14:02 12/12/2025
Total Number of Bidders
2
Technical Evaluation
Number Right Scoring (NR)
Estimated price
755.521.389 VND