Status
Tender opening completed
Bidding package name
Package 06: Construction work
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
The project of upgrading and expanding the road on the south bank of the village canal
(Section from Residential Area to Channel 1)
Contract execution period
120 day
Contractor selection methods
Competitive Bidding
Award date
09:30 03/08/2023
Bid opening completion time
09:31 03/08/2023
Total Number of Bidders
2
Technical Evaluation
Number Right Scoring (NR)
Estimated price
1.556.874.000 VND