Status
Tender opening completed
Bidding package name
Package 06: Construction work.
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Contractor selection plan for the project to build a road from the center of Tien Hoang commune to Da Si lake, Cat Tien district
Contract execution period
24 day
Contractor selection methods
Competitive Bidding
Award date
08:00 05/02/2025
Bid opening completion time
08:04 05/02/2025
Total Number of Bidders
8
Technical Evaluation
Number Right Scoring (NR)
Estimated price
25.429.331.698 VND