Status
Tender opening completed
Bidding package name
Package 06: The whole construction part
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Approval of additional contractor selection plan Project: Renovating and upgrading the infield irrigation system combined with roads in Dong Quang commune
Contract execution period
330 day
Contractor selection methods
Competitive Bidding
Award date
15:00 22/12/2025
Bid opening completion time
15:03 22/12/2025
Total Number of Bidders
2
Technical Evaluation
Number Right Scoring (NR)
Estimated price
32.572.391.761 VND
View by batch
View by contractor