Status
Tender opening completed
Bidding package name
Package 08: Construction work
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
The contractor selection plan for the project package: renovating, repairing damage, the incident of Ta Hong Ha dike from K136+500 to K149+400, Hung Ha District
Contract execution period
180 day
Contractor selection methods
Competitive Bidding
Contract Type
According to fixed unit price
Award date
09:00 07/10/2025
Bid opening completion time
10:39 07/10/2025
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)
Estimated price
39.694.864.000 VND
View by batch
View by contractor