Bidding package name
Package 15: Supervisory consultancy
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Works: Investment in construction of vertical axes eastern Cau Gie - Ninh Binh highway (section from Chau River to the end of Phu Ly city)
Contract execution period
720 day
Contractor selection methods
Competitive Bidding
Award date
08:10 22/06/2025
Bid opening completion time
08:11 22/06/2025
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)
Estimated price
5.475.494.000 VND