Status
Tender opening completed
Bidding package name
Package 23: Construction of works
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Investing in building N5 route connecting from Ring 5 to QL21 and bridge crossing Day River, Kim Bang Town, Ha Nam Province (Project component 2: Construction investment)
Contract execution period
810 day
Contractor selection methods
Competitive Bidding
Contract Type
According to the adjusted unit price
Award date
22:45 16/09/2025
Bid opening completion time
22:45 16/09/2025
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)
Estimated price
1.042.907.239.000 VND
View by batch
View by contractor