The adjusted cost estimate varies significantly and may affect the contractor selection plan.
The bid price of DONG ANH ELECTRICAL EQUIPMENT CORPORATION - JOINT STOCK COMPANY exceeds the approved limit and does not meet the award conditions (Law on Bidding 2023).
The bid price of THU DUC ELECTRO MECHANICAL JOINT STOCK COMPANY exceeds the approved limit and does not meet the award conditions (Law on Bidding 2023).
The bid price of CAMPHA ELETRICAL EQUIPMENT JOINT STOCK COMPANY exceeds the approved limit and does not meet the award conditions (Law on Bidding 2023).
The bid price of MEE POWER TRANSFORMER MANUFACTURING JOINT STOCK COMPANY exceeds the approved limit and does not meet the award conditions (Law on Bidding 2023).