Status
Complete opening of financial documents
Bidding package name
Tender package No 01: Consulting on preparing construction drawing design and construction estimates
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Project contractor selection plan: Construction of classrooms, administrative area, multi-purpose building and auxiliary items for Lac Vien Secondary School
Contract execution period
60 day
Contractor selection methods
Competitive Bidding
Award date
08:30 28/10/2024
Bid opening completion time
08:32 28/10/2024
Total Number of Bidders
2
Technical Evaluation
Number Right Scoring (NR)
Estimated price
1.569.849.000 VND
View by batch
View by contractor