Status
Tender opening completed
Bidding package name
Tender package No 01: Providing equipment and equipment and construction and installation
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Plan for selecting construction contractors: Investing in upgrading anti -overload transformer station in Ho Chi Minh City Electricity. Vi Thanh, TP. Nga Bay & Phung Hiep Electricity
Contract execution period
150 day
Contractor selection methods
Competitive Bidding
Contract Type
According to fixed unit price
Award date
08:00 27/08/2025
Bid opening completion time
08:01 27/08/2025
Total Number of Bidders
6
Technical Evaluation
Number Right Scoring (NR)
Estimated price
14.175.240.867 VND
View by batch
View by contractor