Contractor selection plan and estimates of bidding packages for the preparation phase of investment in the Road project connecting Thanh Hoa city with Ngoc Lac district and western districts of Thanh Hoa province
Contract execution period
45 day
Contractor selection methods
Competitive Bidding
Contract Type
Package and fixed unit price
Award date
10:00 14/04/2026
Bid opening completion time
11:40 14/04/2026
Tender value
Complete opening of technical documents without bidding package price
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)
Information of participating contractors:
Total Number of Bidders: 1
#1
Liên danh Vinasean - Việt Thanh
Business Registration ID ( on new Public Procuring System)