Status
Tender opening completed
Bidding package name
Tender package No 03: Construction cost
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Roads from the root to Mo hill, Thuong Lam commune
Contract execution period
365 day
Contractor selection methods
Competitive Bidding
Award date
15:00 26/06/2025
Bid opening completion time
15:04 26/06/2025
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)