Status
Tender opening completed
Bidding package name
Tender package No 03: Construction works (Including 5% contingency costs)
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Project contractor selection plan: Road from Can village to Ruong village, Bat Mot commune, Thuong Xuan district
Contract execution period
240 day
Contractor selection methods
Competitive Offer
Award date
09:00 24/06/2024
Bid opening completion time
14:08 24/06/2024
Total Number of Bidders
2
Technical Evaluation
Number Right Scoring (NR)