Repair damage to the foundation and road surface of sections Km55+234÷Km55+990; Km65+925÷Km67+029; Km72+139÷Km72+227; Km97+896÷Km98+060; Km98+098÷Km98+159; Km98+913÷Km99+105; Km99+687÷Km99+951; Repair and improve sidewalks and ditches along local sections from Km66+ 352÷Km66+894, Km67+459÷Km67+985, Km72+611÷Km72+704, Km76+827÷Km77+192, Km77+676÷ Km77+938, Km80+078÷Km80+130, Km80+241÷Km80+730, Km84+140÷Km84 +195; Km83+505 sewer, improving traffic safety system at section Km55÷Km100, National Highway 40B
Contract execution period
30 day
Contractor selection methods
Competitive Bidding
Contract Type
All in one
Award date
10:00 20/12/2024
Bid opening completion time
10:17 20/12/2024
Tender value
Complete opening of technical documents without bidding package price