Status
Tender opening completed
Bidding package name
Tender package No 04: Procurement of model building materials in Thanh Hoa and Ha Tinh provinces
Investor
Văn phòng Trung ương Hội Nông dân Việt Nam
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Implementing the project "Building a model for developing commercial chicken farming towards biosafety in the period 2024-2026" in 2024
Contract execution period
45 day
Contractor selection methods
Competitive Offer
Award date
08:12 25/07/2024
Bid opening completion time
11:13 25/07/2024
Total Number of Bidders
2
Technical Evaluation
Number Right Scoring (NR)