Status
Tender opening completed
Bidding package name
Tender package No 06: Construction construction
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Construction of technical infrastructure of Cau Ke resettlement area Phuc Lai commune, Doan Hung district
Contract execution period
90 day
Contractor selection methods
Competitive Offer
Contract Type
According to fixed unit price
Award date
15:15 28/06/2025
Bid opening completion time
16:24 28/06/2025
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)