Status
Complete opening of financial documents
Bidding package name
Tender package No 9: Survey consultancy, construction drawing design and estimation
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Steps to design construction drawings and estimates of the construction project of Dong Kinh bridge, Cho Lach district
Contract execution period
45 day
Contractor selection methods
Competitive Bidding
Award date
15:00 20/10/2025
Bid opening completion time
15:00 20/10/2025
Total Number of Bidders
4
Technical Evaluation
Number Right Scoring (NR)
Estimated price
1.910.396.089 VND