Status
Tender opening completed
Bidding package name
Tender package No: Construction and equipment
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
LCNT plan for the project: Medium voltage transmission line and substation group 17, Tan Tien hamlet
Contract execution period
60 day
Contractor selection methods
Competitive Bidding
Award date
17:15 03/10/2022
Bid opening completion time
17:15 03/10/2022
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)
Estimated price
1.297.670.391 VND