Status
Tender opening completed
Bidding package name
Processing cluster capacity of 2,500 m3/ng
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Works: Hon Dat district water supply system; Category: 2,500 m3/day processor.
Contract execution period
120 day
Contractor selection methods
Competitive Bidding
Award date
09:00 19/09/2025
Bid opening completion time
09:02 19/09/2025
Total Number of Bidders
4
Technical Evaluation
Number Right Scoring (NR)